Development Approval Process

Kojonup Wind Farm submitted a development application to the Shire of Kojonup for assessment under the
DAP Pathway on 06/11/25. Once accepted as suitable for the DAP Pathway applications are progressed as follows:

1

INTENT TO LODGE

Where available, the applicant can discuss the proposal with local government at a pre-lodgement meeting.

2

LODGEMENT WITH LOCAL GOVERNMENT

Application is lodged with Local Government, who confirms that the DAPs pathway is appropriate
to the application

3

LOCAL GOVERNMENT NOTIFIES DAPs OF THE APPLICATION

Local Government notifies the DAP Secretariat, who acknowledges receipt with the local government
and the applicant.

4

ASSESSMENT BY THE RESPONSIBLE AUTHORITY

The responsible authority (mainly local government) assesses the application and prepares a report
to the relevant DAP.

5

DAPs MEETING

The DAP Secretariat prepares a meeting agenda which is published on this website. Local government will notify interested parties. A meeting is held to consider the application.

6

OUTCOMES

DAP makes the decision, which will be determined as approved, refused or deferred. This will be published in the meeting minutes on this website